Development Planning as of Jan 13, 2014
3 Month Planning
This is approaching the limits of what we can do in 3 months but the things that fall off the back end will probably be priorities in the next 3 month cycle.
 
Mobile
-  SmartPlan IOS (Mike, Focalshift) 
-  Deferred Uploader Android Service (Mike) 
-  Access SmartTrack Management  API- 's (Mike) 
-  SmartTrack Finish (Bill) 
-  SmartBlade Start - (Machine Control) (Bill) 
-  Amazon Server Redundancy Implementation (Mike) 
 
Desktop
Trackwork
Materials/Underground
This project will take longer than three months to complete and should be considered a future foundation for other products.
-  New 4D Platform - 
-  Common File Format - simple interchange between Sitework and Materials. 
-  Multiple monitor support 
-  Floating controls/windows 
-  64 Bit 
-  International Support (text broken out for easier translation) 
 
-  True 3D support (sloped areas, sloped structures, using Sitework surfaces) 
-  Structure entry (Pipe, UG structures, retaining walls, abutments) 
-  New Print Page 
-  Pipe and other structure visualization 
-  Completion time assignment/Playback 
-  Linkable (http) field/notes (used in mobile apps for supplier/vendor information 
-  Transfer of Structures to Sitework Sectionals. Two-way data transfer 
-     
 
6 Month Planning
Mobile
-  AGTEK Access Drive Explorer implementation (ala' Dropbox) (Mike ) 
-  Android Tablet optimized layouts (partial, some new layouts are implemented in SmartPlan and SmartTrack) 
-   
 
Desktop
Materials/Underground
Continues from 3 month plan
 
12 Month Planning
Mobile Planning as of March 20, 2013
3 Month Planning
This is approaching the limits of what we can do in 3 months but the things that fall off the back end will probably be priorities in the next 3 month cycle.
-  Leica Cell Driver (Mike) 1.0 
-  Topcon SR Radio and Cell compatibility(when available) (Mike) .1 
-  SmartGrade Labeling and Progress Topo (Bill) .8 
-  Access  API-  for IOS client (depends on hire schedule) (Mike) 1.0 
-  ADF to 4D import  API-  (Bill) 1.0 
-  ADF Writer functionality expansion (Bill) .66  
-  Deferred Uploader/Android AGTEK Access (Mike)  
-  SmartPlan for Android/IOS (Bill, Mike, Consultant to be named later) 
-  Amazon Server Redundancy Planning & Implementation (Mike) 
 
6 Month Planning
-  AGTEK Access Drive Explorer implementation (ala' Dropbox) (Mike ) 
-  SmartTrack 
-  Android Tablet optimized layouts 
-  Trimble Driver SmartGrade 
 
12 Month Planning
Mobile Planning as of December 19, 2012
3 Month Planning
In general order of implementation (barring impediments like no cell subscription)
-  SmartGrade RTK - Altus Cell Driver (Mike) 
-  Base Station Setup - Topcon Driver (Mike) 
-  AGTEK Access Setup 
-  SmartDirt Picture Point Tracking (Mike) 
-  SmartGrade RTK - Stockpile (Bill) - includes Collada Export 
-  SmartGrade RTK - Progress Topo 
-  Access  API-  for IOS client (depends on hire schedule) (Mike) 
-  ADF to 4D import  API-  (Bill) 
-  Amazon Server Redundancy Planning & Implementation (Mike) 
 
6 Month Planning
Since this is farther out, the order of projects is much more variable. 
 
12 Month Planning