Notes
Rectangular pipe can be represented as a tab as shown here but could just as easily be a radio button that changes the interface. Your choice.
We lost the ability to do benches in Underground and it's a big omission since they represent a large number of takeoffs where a flare alone isn't sufficient. We need to model this correctly
Backfill compaction is pretty important when calculating the remaining spoils. It's another thing we lost at some point and need back.
It's not uncommon that none of the trench spoils can be reused for backfill. In those cases there's a need for the select backfill to fill up the trench back to the grade used to enter the pipe. Checking this box does that without requiring specifying a value. This was a feature of old Edge underground but you had to remember to type a . in for a value.
Using the trench spec window to create a template for the trench in Gradework and also create a surface there. This ties the programs together and reinforces the modeling aspect in Gradework. The trench should daylight to whatever the selected surface is rather than just existing or subgrade. We should also consider using the Highway perimeter snugging routine to do the same to trenches rather than copying and clipping from the original surface.
The depth brackets function is complete compared to previous versions but has additional breakdown
Here's a typical report:
Should we default label pipes, structures and fittings? For example if I enter in pipe label the line between each point 8“ SD -1, -2, -3 and break those out in reports. The user could customize the label
We need a quantity report in the Underground program itself. If pipe runs were labeled then breaking out and subtotaling those values also becomes easier as well as showing rock quantities.
Wishlist: Choose colors for strata. All of them being red doesn't help distinguish them. Some sort of legend would help too