With SmartDirt 1.0 completed (December 2011), we're over due to analyze the measured results of the SmartDirt team. This page will summarizes the actual SmartDirt effort and durations, and computes the teams velocity. Velocities can be used to calculate estimates and predictions of future projects.
First, the raw data:
Story | Estimate (ideal days) | Measured | Effort Velocity | Calendar Duration | Calendar Velocity |
0 | 8 | 4.25 | 1.88 | 2 | 4.00 |
1 | 26 | 30 | 0.87 | 31 | 0.84 |
2 | 44 | 42.1 | 1.05 | 35 | 1.26 |
3 | 51 | 57 | 0.89 | 35 | 1.46 |
4 | 37 | 99 | 0.37 | 29 | 1.28 |
5 | 65 | 32.5 | 2.00 | 140 | 0.46 |
6 | 26 | 27 | 0.96 | 60 | 0.43 |