Story 0 - Foundation

Start 2011-01-17

Task Number Owner Estimate Actual Status Description
0.1 M & M 1 1 Done Develop stories, task lists, estimates
0.2 Mike A 1 1 Done AGTEK Access familiarization, development setup
0.3 M & M 2 1 Done Interview Dave RE: Client API functionality
0.4 Mike C 1 Open Mockup key mgmt tool
0.5 Mike A 2 1 Done Define Abstract Key model
0.6 Mike A 2 2 Done Define DB schema for key-stuff
Total 9 6

Story Velocity == 1.5

Complete 2011-01-24 (mja developer time)

Story 1 - Core Implementation / SmartDirt Release

Start 2011-01-25

Task Number Owner Estimate Actual Status Description
1.1 Mike A 1 1 Done Schema creation for new customer DB
1.2 Mike A 1 1.5 Done Alter schema for existing cust DB
1.2.A Mike A 2 Done Announcment API objects
1.3 Mike A 3 1 Done Key API object (client side)
1.3.A Mike A 3 3 Done Local license encrypt.
1.4 Mike A 3 2 Done Support Key API (client side)
1.5 Mike A 3 3 Done Key signing
1.6 Mike A 3 2 Done Protobuf Key API (both) & skel handlers
1.7 Mike A 3 2.5 Done Key creation handlers
1.8 Mike A 3 2.5 Done Client key api handlers
Total 27 19.5

Complete 2011-02-28

Velocity 1.4

Story 2 - C API release

Start 2011-02-28

Task Number Owner Estimate Actual Status Description
2.1 Mike A 3 8 Done C API application level
2.1.A Mike A 3 2 Done C Local license encrypt/Signing
2.2 Mike A 3 4 Done C API support level
2.3.A Mike A 2 0 Done Access/License bits in cust, alter support tool
2.5 Mike A 3 3 Done Key sweep/timed feature sweep/log sweep
Total 14 17

Complete 2011-03-25

Story 3 - Rollout Planning

Start 2011-03-28

Task Number Owner Estimate Actual Status Description
3.1 Mike A 2 2 Done Plan & deploy Access Server
3.2 All 1 1 Done Roll products to use Access server (not key2)
3.3 Mike A 1 1 Done Backup DBs to key2.
3.4 Mike A 1 1 Done Provision Key 2.
3.5 Mike A 1 1 Open Test live rollover.
Total 6 6

Estimation was not done before story commenced, so velocity is meaningless.

Done 2011-04-01

Story 4 - Post roll out completion

Start 2011-mm-mm

Task Number Owner Estimate Actual Status Description
1.9 Mike A 3 Open Stopgap report
2.3 Mike A 5 Open Key create tool
2.4 Mike A 5 Open Document API additions
4.1 Mike A Open Transfer key / user functionality
Total 6 6