Sprint 5A - 2015 Maintenance

Start 2015-04-10

Task Number Owner Estimate Actual Status Description
5.2 WebApplcation
5.2.1 Mike A 0.0 Done Add “.kml” to track download
5.2.2 Mike A 3 Better display of vehicle configuration.
5.2.3 Mike A 3 0.5 Done Allow for edit of alias on trackers.
5.2.4 Mike A 2 Implement “Map All Trackers” button on trackers page
5.2.5 Mike A 0.0 Done Tacks page, remove “Name”, change Vehicle to source, V or T, entry should href to vehicle or tracker entry
5.2.6 Mike A 0.0 Done Track statistics, remove NAME column
5.2.7 Mike A 0.5 1.0 Vehicle page, associate with Tracker, edit details, file Clean up, need set job? Also link to tracker.
5.2.8 Mike A 0.5 1.0 Tracker page, edit associate with Vehicle (perhaps vehicle page?), clean up tracker page in general, add sorting
5.3 Reports
5.3.1 Mike A 0.5 0.5 Done Fix writing of products to be fixed width, w/ leading zeros. See if there is a way of retrofitting existing db.
5.3.2 Mike A 5 2 Done Fix utilization report for John
5.4 API
5.4.1 Mike A 3 Fix getConfiguration to include some filtering args (serial)
5.4.2 Mike A 0.5 0.8 Done Test and verify “out of space” exception for Windows clients
5.4.3 Mike A 0.5 0.7 Done Test and verify lastMod setting from client (And & Windows)
5.4.5 Mike A 3 0.4 Done Lock out application update API, support tool iface
5.6 Bugs
Accserv-17 Mike A 0.5 0.1 Done Prevent slashes (both kinds) in file and folder names
5.6.1 Mike A 0.5 0.5 Done Fix uptime to be after midnight next day instead of just 24 hours + delta. To prevent drift of uptime snaps.
5.7 Mike A Access client
Accclt-13 Mike A 0.5 0.1 Done Make sure out of space is dealt with
Accclt-8 Mike A 3 Drag-n-drop to windows explorer
Accclt-15 Mike A 0.5 Windows install sets install to 0.0.0
5.7.1 Mike A 5 Archive project to zip file. Specify what gets zipped etc
Total 32 7.1

Story Velocity

Complete

Prediction: The only stories with velocities are Story 1 (1.5) and Story 2 (1.4). Using an average velocity of 1.45 the predicted end of work is May 13, 2015 (30 work days).

Sprint 5B - 2015 Maintenance

Start 2015-04-10

Task Number Owner Estimate Actual Status Description
5.1 Tracks
5.5 Architecture
5.5.1 Mike A 1 Characterize current file store performance
5.5.2 Mike A 5 Design HSM flow and table structure
5.5.3 Mike A 5 Implement HSM for files
5.5.4 Mike A 3 Implement HSM for tracks
5.5.5 Mike A 3 Test dual server install, requires HSM, rollover DNS
Total 17 X

Prediction: 12 actual, using velocity of 1.45.